« Getting Unstuck: 30 Years in Low-Earth Orbit | Main | Out of the Abyss »

May 30, 2008

TrackBack

TrackBack URL for this entry:
http://www.typepad.com/services/trackback/6a00d8341bf67c53ef00e552911c6c8833

Listed below are links to weblogs that reference The Come-Back Kid:

Comments

Feed You can follow this conversation by subscribing to the comment feed for this post.

Vincent A. Weldon

June 6, 2008

Why Enterprise Never Went Into Space

by Vincent A. Weldon, Aerospace Bachelor and Master of Science Engineer

Before addressing Enterprise it is helpful to understand two prior experiences that helped me to raise the issue that answers the above question.

In 1960, I was assigned to help design the revolutionary wing trailing edge triple- slotted flap system for Boeing's first highly successful commercial jetliner, the 727, then in development (the 707 was less successful, mainly because of its more numerous variants and fewer sales).

Overall, the detail design, fabrication and testing stages of the 727's development were all conducted in a relatively orderly and predictable fashion, ensuring an on-budget completion. This was partly because not only had an extremely thorough preliminary design stage been conducted, based on the use of mostly proven technology, but also the overall development schedule contained realistic margin for coping with unexpected issues. My job was to design the deployment / retraction system for the outboard aft flap segment, the aerodynamic fairing for its actuator, and its structural attachment to the mid flap. I completed this assignment in mid 1962.

Soon after, I had the opportunity to participate in the development of the Apollo Spacecraft, designing the Lunar Module support and release system as well as the thrust structure for the Service Module's main engine. This program suffered from a very cursory preliminary design phase which even included that, at the time of the Apollo Program award, it had not yet been determined that a “Lunar Orbit Rendezvous” (LOR) approach would have to be used to reduce the overall Spacecraft weight so that the mission could be accomplished by the Saturn V launch vehicle.

As a result, the Spacecraft was designed in two blocks, with Block I being used for unmanned test flights, and Block II being manned. The differences between these block designs were considerable and expensive. But they were accommodated concurrently in such a way that the overall schedule was not seriously impacted. The concern that I was assigned to deal with was that the Block II Service Module required a 100% increase in stiffness, over that of the Block I design, in the main engine thrust structure / actuator loop. This was due to a dead-band limit in the control system, with engine firing when the Lunar Module was docked to the front of the Command Module, during trans-lunar injection. I was assigned to design a new thrust structure which would allow this doubling of stiffness without increasing the weight of the Service Module, which I successfully accomplished.

Despite such unexpected issues, including a tragic ground test fire in which three Astronauts were killed, the goal set by President Kennedy, to accomplish a manned Lunar landing before the end of the decade, was met in mid 1969. This was largely because the 8 year schedule, to first manned Lunar landing, that Kennedy had wisely mandated, inherently accommodated having to cope with major unforeseen problems. The Apollo development program, thus proved to be successful, and the following well-known operational program succeeded beyond all expectations.

Certain little known astute management decisions, which may have saved the Shuttle Program, were made by Prime Contractor and NASA management early in 1974, about two years after the Space Shuttle Orbiter Program was won by Rockwell International. Shortly after serving as Contractor Preliminary Design Review (PDR) Team Leader for the Orbiter Aft Fuselage, at which our preliminary design was approved by NASA, I was shown by the structural analysis supervisor on our team (Pierre “Pete” Dupaquier) that new design loads (including dynamic ones) were about to be surfaced that would, in key areas, exceed those that were driving, particularly, the current structural design of the Orbiter 101 aft fuselage thrust structure. This was a very complex and expensive design, which was one of the first composite (Titanium/ Boron Epoxy) reusable aerospace major primary structure applications.

I immediately scheduled a meeting with the Orbiter Program Chief Engineer (Ed Smith, who had served well in this position on the Apollo Program) . We briefed him in detail, causing him obvious dismay as he asked: “What am I going to tell the Program Manager (George Jeffs)?” Ed saw that we were trying to raise a key issue in time to do something about it before an even worse situation developed and he did not resort to denial or “shoot .the messengers.” We agreed that a meeting would be held as soon as possible to focus on trying to devise a plausible work-around. The problem to be addresses was how to demote “Enterprise” from orbital flight status to “Hanger Queen” without having to build a new orbiter to replace it, a cost impact that would probably end the Shuttle Program and besmirch the reputations of NASA and Rockwell.

The long established Orbiter Vehicle (OV) build schedule at that time was was:1) OV-101 (“Enterprise”); 2) STA-099 (Static test article, which was planned to be static strength tested to destruction); 3) MPTA-098 (Main Propulsion Test Article, consisting of an aft fuselage plus main engines (of about 400,000 lb sea level thrust each) plus a forward truss to simulate the orbiter mid and forward fuselages) for firing at Stennis Space Center; 4) OV-102 (“Columbia”); 5) 0V-103 (“Discovery”); OV-104 (“Atlantis”). Note that “Enterprise” was originally given a 100s number because it was indeed intended to be an orbital vehicle, and STA-099 was indeed intended to be static strength tested to destruction.

A few days later the work-around meeting was held and within less that an hour, as I recall, the problem was resolved. The meeting had barely started when the President of the Shuttle Orbiter Division (George Merrick) asked me why the STA needed to precede MPTA. I answered that, in my opinion, it didn't and this build sequence had only been implemented because a strong supervisor personality in the propulsion group had insisted that MPTA use the same structural design as STA for optimal test results. To me, it was far more important to design STA to withstand the latest loads, by interchanging it with MPTA in the schedule, plus we needed more time to reduce weight. This approach could be implemented by merely testing STS to design (limit) loads to insure that these could be reached without causing significant yielding (plastic strain). This would not only allow STA to be static strength and vibration-tested, but also, STA could be eventually turned into a flight orbiter, eliminating any need to build another entire orbiter from scratch to replace the structurally inadequate “Enterprise.”

Concurrently, a new aft fuselage could be built using the 101 design for MPTA ground testing. Since main engine full thrust cannot be reached at sea level with the throat / bell exit expansion ratio optimized for optimum specific impulse at vacuum conditions, only relatively slight modification of the 101 aft fuselage structure design, would likely be required. Also, Enterprise could still be used for approach and landing tests as well as facility checks before being relegated to museum status (where it currently resides at the Steven Udvar-Hazy Aerospace Museum).

We all seemed to realize that this strategy would be acceptable to NASA since it appeared to enable, overall, a win -win situation for both them and Rockwell. So, there were generally smiling faces as we left the meeting. I could hardly wait to tell my group the good news. Shortly thereafter I got an award from George Jeffs, but only after NASA had agreed with this overall strategy. Anyone who believes the claim that “Enterprise” was never intended to go to orbit, has not researched the original Shuttle Proposals. Incidentally, all one needs to do is peek inside “Enterprise's” aft fuselage and view the partly machined thrust structure cross-beams to which the dummy main engines are attached (if access can be obtained, which is doubtful).

To me, the bottom line is the lesson to be learned from this now documented ethical response to a technical crisis: addressing a technical crisis early and head-on is greatly preferable to denying it, especially incrementally, thus causing much greater financial and reputation loss

Verify your Comment

Previewing your Comment

This is only a preview. Your comment has not yet been posted.

Working...
Your comment could not be posted. Error type:
Your comment has been posted. Post another comment

The letters and numbers you entered did not match the image. Please try again.

As a final step before posting your comment, enter the letters and numbers you see in the image below. This prevents automated programs from posting comments.

Having trouble reading this image? View an alternate.

Working...

Post a comment

About the Author



  • Blog Author Irene Klotz has covered the space program for 21 years. She is based in Cocoa Beach, Fla.

Advertisement